If the activity for which you want to provide variable values is locked, select
Release.
Select Perform.
A list of variables configured for the activity appears.
Enter values for each variable in the SPEC column.
The SPEC column indicates whether the value is in the acceptable range using a color coding, which is configured in Plant Applications Administrator. The quartile chart and the whisker chart are updated.
The SPEC column indicates whether the value is in the acceptable range using a color coding, which is configured in Plant Applications Administrator. The quartile chart, whisker chart, and the SPC chart are updated.
What to do next
If you have provided values for all the variables in the activity, complete the activity. Depending on the configuration, if the activity is overdue, it may be mandatory to enter an overdue comment. If yes, before you complete the activity, you must add an overdue comment. You can choose to also add a general comment for the activity or a comment for the variable.