Use a preconfigured fault resource in a subprocess

Before you begin

You can add only one preconfigured fault for each fault activity. You must also ensure that there is at least one activity following the fault activity.
Note: Activities can be inserted at both the workflow and subprocess levels.

Procedure

  1. In the navigator, click Workflow > Workflows.
  2. In the Workflows list, select the resource you want to work with
    Note: A resource must already have been added in order to select it from this list. For more information, see Add a resource to the workflow model.
  3. In the Displays panel, click Workflow Management > Workflow Editor.
  4. Click the Workflow Editor tab.
  5. Insert an activity:
    • At the workflow level:
      • From the Standard Activities panel, click and drag the activity you want to insert to a drop point.
      Note: Activities can exist only between the presubprocess and postsubprocess.
    • At the subprocess level:
      • Double-click the local subprocess you want to add the activity to.
      • From the Standard Activities panel, click and drag the activity you want to insert to a drop point.
  6. On the activity configuration panel, click Select Fault.
    The Universal Browser appears.
  7. Select the fault you want to add to the fault activity, and then click OK.
  8. Click Save.
  9. Test the workflow and view the results. The workflow terminates with the message specified in the fault resource.