Pipeline ASM Integration
About Asset Strategy Management (ASM) Integration
You can promote an asset to ASM if all the components in the asset have an active RBI Criticality Analysis. When you promote an Asset:
- Degradation Mechanisms (DMs) are used to create Risks in ASM.
- Recommendations are used to create Actions, which are converted to Inspection Tasks. These tasks are listed in Inspection Management.
Details
You can decide on how you want to track recommended actions based on risk information in the DMs. You can choose either of the following options:
-
You will create or generate RBI Recommendations to record recommended actions and mitigated risk values, and then transfer them to ASM. Actions are created for these Recommendations. You will then create Inspection Tasks.
-or-
- You will not create RBI Recommendations. Instead, you will recommend future action and manage mitigated risk values using Actions in ASM.
To transfer RBI Recommendations to Asset Strategies in ASM, you must promote the corresponding asset to ASM. Remember that a single asset can have multiple RBI Components, and each RBI Component can have only one active RBI Criticality Analysis.
After you promote an asset to ASM:
- All the RBI Criticality Analyses and RBI Recommendations linked to the RBI Components in the asset are set to the Accepted by ASM state. You cannot modify them.
- The Mitigated Risk and Mitigated Financial Risk fields on the RBI Criticality Analysis datasheet are disabled.
- If you create another RBI Criticality Analysis for an RBI Component linked to the asset, you can promote that asset to ASM again after changing the state of the new analysis to Risk Completed.
- If you change the state of the analysis to Re-evaluating, and if you want to promote the asset to ASM again, you must first create a new RBI Criticality Analysis and RBI Recommendations for a component in the asset before promoting.
Example: ASM Integration
In the following image, Equipment A is linked to two RBI Components, Component 1 and Component 2, which are each linked to an RBI Criticality Analysis, Analysis 1 and Analysis 2, respectively. If you promote Equipment A to ASM, both Analysis 1 and Analysis 2 are set to the Accepted by ASM state.
Managing Asset Strategies that Were Created from RBI
After an Asset Strategy has been created from RBI, you can manage the Asset Strategy using ASM. Some restrictions will apply to the Asset Strategy, however, depending on how the administrative settings are configured. The following tables provide information on which actions are always allowed, which ones are always restricted, and which ones are allowed only if the appropriate administrative settings are configured.
Always Allowed | Always Restricted |
---|---|
|
|
Allowed Depending on Administrative Settings
The following table describes actions that are allowed for Asset Strategies that were created from RBI and the corresponding administrative setting that allows it.
Action |
Corresponding Administration Action |
---|---|
Opening the Risk Matrix to view the unmitigated risk rank for any Risk that was created from RBI. |
This action is allowed only if the Risk Assessment Enabled check box is selected. If the Risk Assessment Enabled check box is cleared and you click the hyperlinked unmitigated risk rank, a message appears, indicating that you need to view the unmitigated risk values in RBI (i.e., using the Degradation Mechanism datasheet). |
Opening the Risk Matrix to view the mitigated risk rank for any Action that was created from RBI. |
This action is allowed only if the Risk Assessment Enabled check box is selected. If the Risk Assessment Enabled check box is cleared and you click the hyperlinked mitigated risk rank, a message appears, indicating that you need to view the unmitigated risk values in RBI (i.e., using the Degradation Mechanism datasheet). |
Copying a Risk that was created from RBI. |
This action is allowed only if the Risk Assessment Enabled check box is selected. |
Unlinking a driving RBI Recommendation record from an Action. |
This action is allowed if the Risk Assessment Enabled check box is cleared. |
Linking a new Recommendation record to an Action that was created from RBI. |
This action is allowed if the Risk Assessment Enabled check box is cleared. |
Clearing the Drives Action check box for an RBI Recommendation record that was used to create an Action. |
This action is allowed if the Risk Assessment Enabled check box is cleared. |
Asset Strategy Management (ASM) Integration Workflow
This workflow provides the basic, high-level steps for promoting an Asset to ASM.
- Create a Pipeline Component for each piece of equipment.
- Create an RBI Pipeline Analysis for the component.
- Assess the unmitigated risk of the Degradation Mechanisms (DMs) that are linked to the RBI Pipeline Analyses.
- Change the state of all the RBI Pipeline Analyses to Risk Completed.
- Generate Recommendations for all the analyses within the asset, and asses the mitigated risk.
-
This will promote all the RBI Recommendations and DMs associated with the Asset to ASM.
Promoting an Asset to ASM includes steps to analyze the risk associated with each component, recommend future action based on the risks, and transfer the analysis data to ASM. You can recommend future action in one of the following ways:
- Using RBI Recommendations in RBI: In this workflow, you will identify the mitigated risk of DMs in RBI.
- Using Actions in ASM: In this workflow, you will identify the mitigated risk of DMs in ASM.
In most cases, you will complete the steps in either workflow on a regular basis as you refine the operating conditions and environment. RBI Analyses are dynamic tools that help you refine your strategy for maintaining RBI Components.
About Unmitigated Risk
When you calculate an RBI Criticality Analysis, the unmitigated SHE risk and unmitigated financial risk for each Degradation Mechanisms record (DM) are calculated automatically, and stored in the DM. The calculation is performed using Risk Mapping Policies.
Unmitigated Risk
The unmitigated risk rank is plotted on a Risk Matrix. This value is the intersection of the consequence and probability that are calculated when you calculate an RBI Criticality Analysis.
-
Consequence of Failure: The consequence of failure is the highest among the values in the following fields in the associated Criticality Consequence Evaluation:
- Flammable Consequence Category
- Toxic Consequence Category
-
Environmental Consequence Category
Note: The Environmental Consequence Category field contains a value only if the RBI Component contains the value Storage Tank - Bottom in the Component Type field.
- Probability of Failure: This value is calculated and stored in the DM.
GE Digital APM then locates the Risk Translation record with this temporary unmitigated risk value in the Source Risk Rank field and the value No (N) in the Financial? field.
Unmitigated Financial Risk
The unmitigated financial risk rank is plotted on a Risk Matrix. This value is the intersection of the consequence and probability that are calculated when you calculate an RBI Criticality Analysis.
-
Financial Consequence: The financial consequence is the highest among the values in the following fields in the associated Criticality Consequence Evaluation:
- Lost Production Category
-
Product Leak Category
Note: The Product Leak Consequence field will contain a value only if the RBI Component contains the value Heat Exchanger - Bundle in the Component Type field.
- Probability of Failure: This value is calculated and stored in the DM.
GE Digital APM then locates the Risk Translation record with this temporary unmitigated risk value in the Source Risk Rank field and the value Yes (Y) in the Financial? field.
About Mitigated Risk
When you calculate an RBI Criticality Analysis, the unmitigated risk and unmitigated financial risk for each DM is calculated automatically and stored in the related Degradation Mechanisms record (DM).
By default, the mitigated risk values are set to the same values as the unmitigated risk values. You can modify the mitigated risk values manually using the risk matrix to indicate how the risk could be lowered if certain actions were taken.
Promote an Asset to Asset Strategy Management (ASM)
Before you begin
- All the Pipeline Components linked to the Asset must contain an active RBI Pipeline Analysis (i.e., in Risk Completed state).
Procedure
Results
- If the selected asset is not currently linked to an Asset Strategy, a new Asset Strategy is created and linked to the asset.
- All the Degradation Mechanisms (DMs) and Recommendations linked to the Asset are promoted to ASM.