Change the Work Order Plan

Before you begin

If you do not have the permission to perform this task, a message appears, stating the same. If that happens, request your administrator to provide the permission using Security.

About this task

This topic describes how to modify a work order's details such as planned start and end dates and priority.

Procedure

  1. Access the work order whose plan you want to modify.
  2. In the upper-right corner of the page, select , and then select Edit work order plan.
    The Edit Work Order Plan window appears.
  3. As needed, modify the planned start and end dates and priority of the work order.
  4. Select Update.
    The changes made to the work order are saved.