Depending on the type of risk or action that you want to create, select the appropriate drop-down, and then follow the contained steps.
Steps
In the Risks and Actions workspace, at the top of the grid, select
The column positions are switched. The Actions column is now the left column.
In the upper-left corner of the Actions column, select
A blank datasheet appears for the new action record.
As needed, enter values in the available fields and use the risk matrix control to assess the risk.
Select
The record is saved.
In the upper-left corner of the Risks column, select
A blank datasheet appears for the new risk record.
As needed, enter values in the available fields and use the risk matrix control to assess the risk.
Select
The record is saved.
In the upper-left corner of the Mitigating Actions column, select
A blank datasheet appears for the new action record.
As needed, enter values in the available fields and use the risk matrix control to assess the mitigated risk.
Select
The record is saved.
In the Risks and Actions workspace, at the top of the grid, select
The column positions are switched. The Mitigated Risks column is now the right column.
In the upper-left corner of the Mitigated Risks column, select
A blank datasheet appears for the new mitigated risks record.
As needed, enter values in the available fields and use the risk matrix control to assess the unmitigated risk.
Note: You will only be able to do an unmitigated assessment in this view before saving the new risk. After that, to edit the unmitigated risk assessment, you must switch the column positions by selecting
Select
The record is saved and the unmitigated risk assessment is used to initialize the mitigated risk assessment.
Select
The risk is saved.