Add a Route

About this task

This topic describes how to create a route. You can also copy an existing one.

Before you begin

  • Ensure that the production line that you want to use is route-enabled. When you do so, a virtual unit is created on the line, and a path is created on the line that contains the virtual unit.
  • Associate the material with the virtual unit on any line where you want to produce the material
  • Ensure that a BOM formulation is defined for the material. This is required if you want to leverage raw material tracking in the route.

If these components do not exist, contact the Plant Applications administrator.

Procedure

  1. In the Route Editor page, select .
    The Create Route window appears. The REVISION box is disabled and populated with the value 1 because this is the first draft of the route.
  2. Provide values as specified in the following table.
    FieldDescription
    NAMEEnter a unique name for the route that does not exceed 100 characters.
    DESCRIPTIONEnter a description for the route that does not exceed 1000 characters.
    PRODUCTION LINESelect a production line to which the route belongs. This box contains a list of production lines defined in Plant Applications Administrator. A value is required in this field.
    MATERIALSelect the material that you want to use in the route. This box is enabled after you select a value in the PRODUCTION LINE box. It contains a list of materials defined for the production line in Plant Applications.
    BOM FORMULATIONSelect the BOM formulation that you want to use in the route. This box is enabled after you select a value in the MATERIAL box. It contains a list of BOM formulations configured for the material in Plant Applications.
  3. Select Next.

Results

The route is created and is in the draft state. The Edit Route page appears, allowing you to create an operation.

What to do next

Add an operation to the route.