Migrating Data into HyperStage

Migrate Data into HyperStage

About This Task

This topic describes how to migrate Work History family data from a source family in APM into the HyperStage PostreSQL database. You can then create visualization on the data.

To migrate the data, an ETL tool named the Advanced Visualization Data Migrator tool is used.

Procedure

  1. Access the Advanced Visualization page.
  2. Select , and then select Prepare and Manage Data.
    The SERVER page appears.
  3. Under Applications, select meridium > work-history > flows.
  4. In the Application Directories section, right-click the flow whose data you want to migrate, and then select Submit.
    The job ID appears in the Submit section.
  5. In the File Panel section, right-click the flow that you have submitted, and then select Logs > Statistics.
    The status of the flow appears (for example, pending, running, done).
  6. Repeat the aforementioned steps for all the flows.

What To Do Next

After all the flows are submitted and the status changes to Done, you can create visualizations on the data via HyperStage.