RBI Bulk Evergreening
About RBI Bulk Evergreening
RBI Bulk Evergreening is the process of duplicating active analyses in bulk based on the associated process unit or functional location. The evergreened analyses use the latest Risk Completed data available to create more up-to-date analyses for the process unit or functional location.
When to Evergreen
When an analysis is initially created, its record contains details that are observed at the time of the assessment. Evergreening is useful when a functional location or process unit has undergone changes. These changes can include the implementation of risk mitigation strategies or maintenance. Additionally, evergreening is useful after a set amount of time has passed since the previous analysis.
Batches
During the duplication process, you select or create an Evergreening Batch ID to group your evergreened analyses. You can filter analyses based on the batch in the RBI Bulk Evergreening workspace. The Evergreen Batch ID that you select will be copied to the Scenario ID field in the duplicated analysis.
Access Analyses that are Pending Evergreening
About This Task
Procedure
- Access Analyses that are Pending Evergreening from the RBI Bulk Evergreening workspace:
- Access Analyses that are Pending Evergreening from the Risk Based Inspection Overview page:
- Access Analyses that are Pending Evergreening from a Process Unit:
Duplicate Analysis for Evergreening
Procedure
Delete Analyses Created for Evergreening
Procedure
Export Evergreened Analyses
About This Task
Procedure
Calculate Evergreened Analyses
Procedure
Finalize Risk for Evergreened Analyses
Before You Begin
You must calculate risk on an evergreened analysis before finalizing risk.
Procedure
Access Active Analyses
About This Task
Active evergreened analyses are RBI Criticality Analyses for RBI Components linked to RBI Assets. These analyses were created during the bulk evergreening process, and they are not in the Created or Archived state.
Procedure
Generate Recommendations for Active Evergreened Analyses
Procedure
Results
- You can use the Inspection Plan Summary page to approve the Inspection Plan and implement recommendations.
- In the RBI Global Preference settings, if the Enable Recommendation To be Generated at Created State check box is selected, recommendations will not be linked to the Inspection Plan until the related analysis is moved to the Risk Complete state and the Inspection Plan is generated.