Change the State of an SRS Project

Steps

  1. Access the SRS Project for which you want change the state.

  2. In the upper-right corner of the workspace, select the button that indicates the current state of the SRS Project. For example, if the current state of the project is In Progress, select In Progress.

    A menu appears, displaying the list of operations that you can perform on the SRS Project to change its state.

    SRS Project State Menu

  3. Select the necessary operation that will change the state of the project, and then select Done. For example, if you want to change the state of the analysis from Planning to Active, select Begin , and then select Done.

    Note: You can view the states assigned to various users by selecting the Manage State Assignments link. If not already done, you can assign the next state to the appropriate user, and then select Done.

    The state of the SRS Project is changed.

Results

Copyright © 2018 General Electric Company. All rights reserved.