Add a Row in a Production Plan

Steps

  1. Access the Production Plan to which you want to add a row of data.
  2. In the Plan Details workspace, select , and then select Add Row.

    A new row of data is added to the second table. The values in the Start Time and End Time columns and the planned production value for the new row are determined automatically.

  3. The values in the Quantity and End Time columns in the first table and the Plan ID are updated.