In Risk Based Inspection, you can divide equipment into components whose risk you want to analyze using an RBI
In GE Digital APM, the information related to an RBI component is stored in the following Criticality Calculator RBI Component records:
The information related to a PRD component is stored in the following Criticality Calculator PRD Components:
Consider a Heat Exchanger, which is a piece of equipment that contains the following components:
Each of the components can contain items such as Nozzles, Flanges, or Piping.
In RBI, to analyze the ways in which the exchanger can fail, you must divide the components into logical groups that represent common failure characteristics. Each group of components is a separate component and is represented by a single RBI Component record. Keep in mind that some of these groups are involved in the overhead system, and others are involved in the cooling water system.
For example, you might group the equipment's components as follows:
If you create an RBI
Note: If you have already created Functional Location records to represent the OVHD System and Cooling Water System using the recommended asset hierarchy, you must create additional Corrosion Loop records to represent these same systems. The existing Functional Location records need not be linked to the Corrosion Loop records.