Send an EAM Work Request

In the Approved Actions section, you can send a work request or a maintenance plan to create an implementation in the EAM system for the selected Actions.

Steps

  1. Access the Approved Actions section.
  1. In the Approved Actions section, select the check box in each row containing an action that you want to include in the work request.

    IMPORTANT: The maximum number of records that you can selected for one implementation is 250.

    The action(s) are highlighted.

  2. In the workspace, select Implement, and then select EAM Work Request.

    The Implement as EAM Work Request window appears.

  3. Select Send.

    A message appears, confirming that the work request has been sent successfully.

Results

Copyright © 2018 General Electric Company. All rights reserved.