The diagram below shows the workflow of the State Management process as it applies to Inspection Recommendations.
Initial State
The Inspection in Progress state is the initial state of all Inspection Recommendations
Datasheet Configuration
By default, states and operations will appear on the datasheet when you are viewing an Inspection Recommendation or the Record Manager.
Reserved States and Operations
The following table indicates whether or not the baseline states and operations are reserved. You cannot remove or modify reserved states or operations. You can, however, add your own states and operations to the State Assignment
States | Is Reserved? |
---|---|
Accepted by ASM |
Yes |
Approved |
No |
Consolidated |
Yes |
Implemented |
No |
Inspection in Process |
No |
Pending Approval |
No |
Proposed |
Yes |
Rejected |
No |
Superseded |
Yes |
Operations | Is Reserved? | Predecessor State | Successor State |
---|---|---|---|
Approve |
No |
Pending Approval |
Approved |
Consolidate |
Yes |
Proposed |
Consolidated |
Implement |
No |
Approved |
Implemented |
Inspection Completed |
No |
Inspection in Process |
Proposed |
Promote to Action |
Yes |
Proposed |
Accepted by ASM |
Reject |
No |
Pending Approval |
Rejected |
Request Approval |
No |
Proposed |
Pending Approval |
Rework |
No |
Pending Approval |
Proposed |
Supersede |
Yes |
Proposed |
Superseded |
Unlink from Master |
Yes |
Accepted by ASM |
Proposed |
Unlink from Master |
Yes |
Consolidated |
Proposed |
Unlink from Master |
Yes |
Superseded |
Proposed |
Copyright © 2018 General Electric Company. All rights reserved.