Link a Work Pack

Note: This procedure applies to linking existing Work Packs to other Work Packs and Sub Work Packs. GE Digital recommends that you have no more than three levels of Work Packs (i.e., a Parent Work Pack, a Child Work Pack, and a subsequent (or grandchild) Child Work Pack).

Steps

  1. Access the Work Packs section.
  2. In the row containing the Work Pack that you want to access, select the link.

    The Work Pack Overview workspace for the selected Work Pack appears, displaying the Definitions section.

  3. In the left pane, select .

    The Link Existing Work Pack Records to <Work Pack Name> window appears.


  4. As needed, enter values in the available search fields, and then select .

    The Work Packs that can be linked to the selected Work Pack appear.

  5. Next to each Work Pack that you want to link to the Work Pack, select the check box, and then select OK.

    The selected Work Packs are linked.

Copyright © 2018 General Electric Company. All rights reserved.