This procedure will work in both Active and Proposed scenarios.
Steps
Select a scenario, and then, in the workspace, select the Actions tab.
The Actions section appears, displaying a list of available actions.
In the row for the action to which you want to add resources, select the link in the Resource Usage column.
The Resource Usage subsection appears.
In the Resource Usage subsection, select
The Add New Resource Usage datasheet appears.
As needed, enter values in the appropriate fields. When finished, select
The new resource is added to the action.