Resolving Schedules

To resolve a schedule:

  1. In Classic view, from the WorkSpace toolbar, click the Resolve Files Tool button.

-Or-

In Ribbon view, on the Applications tab, in the Utilities group, click Utilities, and then click Resolve Files.

  1. In the File Types area, select the Schedule check box.
  2. In the Directories area, verify that your schedule directory is correct. If it is not, enter the correct path in the Schedules field.
  3. In the Resolve Files area, select the schedule file you want to resolve. To select every file in the list, click Select All.
  4. Click the Update Schedule Files button and then click OK.