Eneva requested support to advance the upcoming outage by more than a month. The GE Vernova team knew Eneva’s overworked turbines could fail trying to fill the energy gap caused by the drought. If they didn’t advance the outage, it could force an uncontrolled emergency outage. GE Vernova agreed, proposing an outage performed in two phases, so Brazil’s power supply remained uninterrupted.
The two entities had a long collaborative relationship, and synergy between them improved with each outage performed. But this acceleration was by no means a guaranteed success—in fact, the 16-day goal seemed nearly impossible at the start.
First, GE Vernova assembled the right team of experts from nearby Peru and Mexico, 90% of whom were experienced in the process. But would the visas come through in time? Eneva’s strong standing with the government helped reduce visa processing time from more than three weeks to just five days.
All tooling, parts and OTD had to be at the site prior to the accelerated outage for the plan to work without disrupting power generation. With the plant’s experience co-managing GE Vernova equipment outages since 2018, they were able to streamline the flow of materials to meet the short deadline.
Typically, a Hot Gas Path (HGP) outage like this one is performed over 15-16 days. In the end, GE Vernova and Eneva achieved a remarkable 14-day HGP for the first outage project and 12-day for the second. These energy partners shared a common goal and achieved on-time delivery with zero accidents and high technical quality.